Skip to main content

Lift Station 14

OPUD has completed the exterior lift station portion of work as of OCTOBER 1ST, 2025. The remaining improvements include interior lift station work that’s to be completed by November 30TH, 2025.

There have been two contractors working on the project:

 

NEWLAND ENTITIES INC

CUSHMAN CONTRACTING CORPORATION.

 

NEWLAND ENTITIES: Have remaining biobed to be completed, required irrigation to biobed, and retaining wall.

 

CUSHMAN CONTRACTING CORPORATION: Below is the work schedule that includes completion items and dates for Cushman Contracting

Lift Station 14 Work Schedule Cushman Contracting Corp.pdf

 

 

 

Street corner with a Zanes Dr. sign, trees, a truck, construction materials, and a fall festival banner.
Two excavators on a gravel area, with trees and a green field in the background.
Construction area with pipes, cones, machinery, and gravel.